Commissioning
By Jerry Yudelson
 

Building commissioning is a high-­value-­added activity that is unknown outside the building industry. Think of a ship; when construction is fin­ished, it’s time for sea trials. Long before a vessel sets out on a mission or voyage, all key systems are tested in calmer waters to make sure everything is working as designed. This includes propulsion, navigation and safety equipment.

Now consider a modern high-­rise building, which is every bit as com­plex as a ship. It’s expected to perform well for decades, supporting all types of occupancy and enduring both normal and extreme weather events, including torrential rains, high winds, tornadoes, floods and hurri­canes, and to be safe for its occupants in the event of fire or earthquake. Shouldn’t this building be commissioned just as a ship would be?  

Posed this way, the answer is obvious. In the past decade, the practice of commissioning for larger buildings has become an accepted practice. The LEED system requires that every project be commissioned according to certain standard procedures. The goal is to test all energy­-using and life-safety systems in actual building operation and to work out all the kinks before occupancy. More than 120 research studies have shown that energy savings increase 10% to 15% when a building is commissioned. In energy savings alone, commissioning pays for itself in less than five years; when other non-­monetary (but real) benefits are included, the return is typically less than one year.

The cost of commissioning is relatively minor compared with the benefits. In larger projects, the cost might range from $0.40 to $1.00 per square foot, less than 1% of building costs. The key to the process is to get experienced commissioning agents on board during the design phase so that they can understand and help clarify the owner’s project require­ments and the engineer’s basis of design. In this way the commissioning agent understands the project’s goals, systems and performance require­ments before testing begins.

A typical commissioning activity involves creating a plan; writing commissioning requirements into the project specifications; engaging the subcontractors during construction — especially mechanical, electrical and controls contractors — to assist with testing; fixing any problems en­countered with system operations; and confirming that operators have been trained to keep the building running optimally.

Some projects also provide enhanced commissioning, including hav­ing a completely independent commissioning agent reporting directly to the building owner (some people think this provides a more objective look at the project functioning), examining design documents well before con­struction starts, and coming back near the end of the warranty period (typically a year) to examine the building performance and correct any deficiencies. Enhanced commissioning also requires someone to prepare a re-commissioning manual for later use, since commissioning is best re­garded as a continuous activity over the lifetime of a building.

 
REFERENCES :
Cost-Effectiveness of Commercial-Buildings Commissioning [3 April 2007]. Available from: http://www.eetc.lbl.gov/Emills/PUBS/Cx-Costs-Benefits/html 
 

Recent Message Board Posts

 

 
 
ecomii featured poll

Are vitamins and supplements effective?

 

 

Are vitamins and supplements effective?
 
the ecomii eight
1 Winter Squash   5 Pistachio Stuffing
2 Chestnuts   6 Cap & Trade
3 Carbon Footprint   7 Pecan Pie
4 Supplements   8 Natural Health
 
ecomii resources
 
ecomii Tips Newsletter 

Sign up today to receive a weekly tip for living greener

 
Get in Touch

Got suggestions? Want to write for us? See something we could improve? Let us know!